VMS Construction - Pictures

Chronological Construction Events

Period

Content

May 2002

Soil is removed from the building site, excavations done for pipes, pump and well. Foundation for the walls was assembled, and the wall units placed.

July 2002

The roof trusses are in place and the ceiling insulation and roof are being mounted.

August 2002

The interior installations start. The tiled milk room is ready and the equipment installed. The office is finished, and the VMS room is ready for the VMS unit. The automatic manure system and feeding system are in place and 3 kilometers of cables is installed in the new barn!

September 2002

The VMS has arrived and installation work can begin. The mats are put in place. The feeding station is supplemented with feeding cubicles and rubber mats. The VMS facility is ready for its first herd. 

December 2002

Pictures from the VMS barn in operation.

January 2004

More pictures from the VMS barn in operation.